Most asphalt runways are resurfaced every 10 to 20 years. The industry rule of thumb is 10 to 15 years, but recent UK projects show how wide the real range is.

Heathrow’s southern runway was resurfaced in 2024, ten years after its previous overlay. Edinburgh went 17 years between full resurfacing projects, and London Luton almost 20.

Where a runway falls in that range depends on its traffic, its climate and the asphalt it was built with. It also depends on how the surface is looked after between major works, and that is the part an airport operator controls.

What decides how often a runway is resurfaced

A runway rarely needs resurfacing because the structure underneath has failed. Far more often, the top layer of asphalt has aged to the point where it can no longer stay intact, drain water or hold its grip. Several things set the pace of that ageing.

  • Oxidation. From the day it is laid, the bitumen binder in asphalt reacts with oxygen and UV light. It hardens, loses flexibility and starts to let go of the fine material and stones it holds.
  • Traffic. Heavier aircraft and more movements wear the surface faster. Touchdown zones and runway ends usually go first.
  • Weather. Water getting into small cracks and freezing opens them up. Long hot spells soften the surface and speed up binder ageing.
  • The original mix. Marshall asphalt, stone mastic asphalt and grooved surfaces all age differently. So does a surface laid in poor conditions or patched many times since.
  • Maintenance in between. A surface that is sealed against oxidation early in its life ages much more slowly than one left untreated until it starts to break up.

Signs a runway is due for resurfacing

The warning signs usually build up over several years before a resurfacing date is set. Airfield managers tend to see the following.

  • Ravelling and FOD. As the binder hardens, loose stones and fines come away from the surface and become foreign object debris. Before Alderney Airport treated its runway, routine FOD sweeps collected more than 400kg of material a month.
  • Cracking. Fine surface cracks let water in and widen with each freeze and thaw.
  • Falling friction. Worn or polished texture shows up in routine friction testing and can put a runway’s surface classification at risk.
  • More reactive repairs. Patching, crack sealing and emergency closures start to take up more of the maintenance budget. Before its 2025 to 2026 resurfacing, Edinburgh Airport had 16 unplanned runway closures for emergency repairs in a single year.

By the time all of these are showing, resurfacing is usually the only option left. Spotting ravelling and early cracking sooner gives an airport more options.

Runway resurfacing: what it involves, closures and cost

Resurfacing means planing off the worn surface course and laying new asphalt, usually with new grooving, markings and lighting at the same time. At a busy airport the work is done in short night-time closures, one section of runway at a time, and the runway goes back into service each morning.

Three recent UK projects show the scale involved.

Globally, a full runway resurfacing typically costs between £10m and £25m. On top of the contract price, the airport has to plan around months of restricted night operations. There is also the carbon cost of producing and hauling tens of thousands of tonnes of new asphalt.

Runway resurfacing alternatives: asphalt preservation

If the asphalt is ageing but still structurally sound, it can be preserved instead of replaced. Rhinophalt® is a preservation treatment sprayed onto the existing surface. It seals the binder against oxygen, water and UV light, which slows oxidation and holds the aggregate in place.

Because it works on the surface that is already there, the numbers look very different from resurfacing.

  • Cost. Treating a runway costs roughly 10% of resurfacing it.
  • Carbon. Carbon emissions are more than 90% lower than resurfacing, because no asphalt is planed off, produced or hauled.
  • Time on the runway. A full runway of around 180,000m² can be treated in less than two weeks of night shifts, and relining can be done in the same shift.
  • Surface life. Preservation can extend the life of the surface course by up to 100%, and it reduces FOD caused by ravelling.

RAF Brize Norton shows what that extra time can look like. Rhinophalt was applied across the full runway in 2017, then across 458,000m² of runway and taxiways in 2020, the largest Rhinophalt project on any airfield. Together the two treatments kept the surface in service for around nine more years, until the runway’s planned full reconstruction began in 2026. At Mackay Airport in Queensland, a five-yearly Rhinophalt cycle is expected to push resurfacing of runway 14/32 back to 2045 or later.

Preservation is not a repair for a runway that has already failed. It works best when it is applied while the surface is still in fair condition, which is why timing matters so much.

Building preservation into your airfield pavement maintenance plan

The runways that go longest between resurfacing projects are usually the ones where preservation is planned rather than used as a last resort. A typical approach looks like this.

  1. Survey the surface. Start with a condition survey and the latest friction test results, so you know which areas are ageing fastest.
  2. Treat early. Apply the first preservation treatment while the asphalt is still in good or fair condition, ideally within the first few years after it is laid.
  3. Reapply on a cycle. Plan repeat treatments, typically every five years, so the binder never reaches the brittle stage.
  4. Reset the resurfacing date. Use the extended surface life to move resurfacing to a year that suits your budget and operations, rather than letting the surface decide.

Frequently asked questions

How often does a runway need to be resurfaced?

Most asphalt runways are resurfaced every 10 to 20 years. The interval depends on traffic, climate, the original asphalt and how well the surface is maintained between major works.

How much does it cost to resurface a runway?

A full runway resurfacing typically costs between £10m and £25m. Recent UK examples include £18m at London Luton and £30m at Edinburgh.

How long does runway resurfacing take?

At a working airport, resurfacing is usually done in night-time closures over five to seven months. Heathrow’s southern runway took 29 weeks in 2024.

Can you extend the life of a runway without resurfacing it?

Yes, if the asphalt is still structurally sound. Preservation treatments such as Rhinophalt® seal the surface against oxidation and can extend the life of the surface course by up to 100%, for roughly 10% of the cost of resurfacing.

What causes FOD on a runway?

On ageing asphalt, a common cause is ravelling. As the binder hardens, stones and fine material come loose from the surface and end up on the runway as debris.

Your Rhinophalt® Journey begins here

Over the last few years, our asphalt preservation webinars have given several local authorities and other organisations a true insight into the benefits of Rhinophalt®, asphalt preservation in the UK and around the globe.

The webinars go into detail about why preservation is important and the benefits of using Rhinophalt®, they explain the simple and cost-effective application process and why it is important to use a trusted, original and authentic source of asphalt preservation.

Contact us today

Understand more about how we can help protect and preserve your roads, airports, bridges and other infrastructure for longer.